Spanish Fork Canyon Pipeline – Reach 3

2.1 Miles 96-inch Welded Steel Pipe

The following information is currently available for Reach 3:

Prequalification Information

Pay Estimates

Tentative Project Schedule

The following is a preliminary schedule and is subject to change:

Pre-qualified Contractors Notified
Tuesday, April 14, 2009
Bid Opening
9:00 am, Tuesday May 19, 2009
Contract Awarded
Wednesday, May 20, 2009
Preconstruction Meeting
Monday, June 15, 2009
Notice to Proceed - Materials
Tuesday, June 16, 2009
Notice to Proceed - Field Construction
Tuesday, September 1, 2009
Start Field Construction
Tuesday, September 1, 2009
Construction Complete
Monday, November 30, 2010

Location Map

General Plan & Profile

Prequalified Bidders List

100% Submittal Documents

Bid Opening Summary

SFCP Reach 3 Monthly Reports