Spanish Fork Canyon Pipeline – Reach 2

2.7 Miles 96-inch Welded Steel Pipe

Construction of the Spanish Fork Canyon Pipeline – Reach 2 will begin in 2009.  Prequalification statements are due to the District on December 12, 2008.  A mandatory pre-bid conference is scheduled for November 21, 2008.  Contract bid documents will be available December 19, 2008 and Bid Opening will be held on January 20, 2009.

Tentative Project Schedule

The following is a preliminary schedule and is subject to change:

Prequalification Statement available for pickup by prospective contractors
Friday, October 31, 2008
Pre-bid conference and site visit
Wednesday, January 21, 2009
Prequalification Statement due at District
Friday, December 12, 2008
Notification of pre-qualified contractors
Thursday, December 18, 2008

Contract documents available

Tuesday, January 6, 2009
Bid opening
Tuesday, January 27, 2009
Award Date
Wednesday, January 28, 2009
Pre-construction meeting
Tuesday, February 3, 2009
Notice to Proceed - Materials
Wednesday, February 4, 2009
Notice to Proceed - Field Construction
Tuesday, May 26, 2009
Start Field Construction
Monday, June 1, 2009
Construction Substantially Complete
Monday, November 30, 2010

The following information is currently available for Reach 2:

Prequalification Information

Notice Inviting Bids

Amended Bid Schedule

General Plan & Profile

Prequalified Bidders List

Spanish Fork Canyon Pipleline - Reach 2 Bid Opening Summary